For sure pass exam with the help of Microsoft 070-178 study material, That's Easy With Easy4Engine!
Last Updated: Jul 28, 2026
No. of Questions: 70 Questions & Answers with Testing Engine
Download Limit: Unlimited
Pass your actual test with Easy4Engine updated 070-178 Test Engine at first time. All the contents of Microsoft 070-178 exam study material are with validity and reliability, compiled and edited by the professional experts, which can help you to deal the difficulties in the real test and pass the Microsoft 070-178 exam test with ease.
Easy4Engine has an unprecedented 99.6% first time pass rate among our customers.
We're so confident of our products that we provide no hassle product exchange.
It can be understood that only through your own experience will you believe how effective and useful our Microsoft Project 2010, Managing Projects exam study material are. When you visit our website, it is very easy to find our free questions demo of 070-178 exam prep material. It is available for you to download and have a free try. Although there are parts of the complete study questions, you can find it is very useful and helpful to your preparation. According to the free demo questions, you can choose our products with more trust and never need to worry about the quality of it. With our Microsoft Project 2010, Managing Projects study material, you can clear up all of your linger doubts during the practice and preparation.
It is well known that Microsoft Project 2010, Managing Projects exam is an international recognition certification, which is very important for people who are engaged in the related field. The preson who pass the 070-178 exam can not only obtain a decent job with a higher salary, but also enjoy a good reputation in this industry. But it is difficult for most people to pass Microsoft Project 2010, Managing Projects exam test. While, our Microsoft Project 2010, Managing Projects practice questions can relieve your study pressure and give you some useful guide. We have been sparing no efforts to provide the most useful study material and the most effective instruction for our customer.
As for many customers, they are all busy with many things about their work and family. So, if there is a fast and effective way to help them on the way to get the Microsoft Project 2010, Managing Projects certification, they will be very pleasure to choose it. Here, our 070-178 training material will a valid and helpful study tool for you to pass the actual exam test. With the Microsoft Microsoft Project 2010, Managing Projects exam training questions, you will narrow the range of the broad knowledge, and spend time on the relevant important points which will be occurred in the actual test. Thus, you will save your time and money on the preparation. After the analysis of the feedback from our customer, it just needs to spend 20-30 hours on the preparation. Through the notes and reviewing, and together with more practice, you can pass the actual exam easily.
Easy4engine are trying best to offer the best valid and useful study material to help you pass the Microsoft Microsoft Project 2010, Managing Projects exam test. We have good customer service. If you have any questions about our products or our service or other policy, please send email to us or have a chat with our support online. Our 24/7 customer service are specially waiting for your consult. We are trying our best to help you pass your exam successfully. Besides, in case of failure, we will give you full refund of the products purchasing fee or you can choose the same valued product instead.
| Section | Objectives |
|---|---|
| Topic 1: Planning Projects | - Define tasks, dependencies, and milestones - Create and configure project plans in Microsoft Project 2010 - Assign resources and optimize schedules |
| Topic 2: Reporting and Communication | - Communicate project status to stakeholders - Generate project reports and dashboards |
| Topic 3: Initiating Projects | - Define project scope and objectives - Identify stakeholders and project constraints |
| Topic 4: Managing and Tracking Projects | - Manage resource allocation and workload - Track project progress and update schedules - Handle project changes and baselines |
| Topic 5: Customizing Microsoft Project | - Customize views, tables, and fields - Configure project settings and templates |
1. John, a team member, will be absent from the team. A new team member, Mary, will take over Johns remaining work. You need to update the project schedule to reflect the change. You also need to retain John's actual work. What should you do?
A) In the Resource Usage view, rename John to Mary.
B) In the Multiple Task Information dialog box, change the resource assignment from John to Mary.
C) In the Resource Sheet view, delete John and add Mary.
D) In the Assign Resources dialog box, use the Replace feature.
2. You need to view only the task name, start and finish dates, percentage of work completed, and a Gantt chart. What should you do?
A) Create a custom filter and a custom view.
B) Create a custom table and a custom view.
C) Create a custom table and a custom group.
D) Create a custom filter and a custom table.
3. Standard working hours are eight hours a day from Monday through Friday. You create a task of fixed units
and set the duration to 2 days. You assign the task to John at 100 percent. John wants to work only 50
percent on the task. You change John's assignment units to 50 percent for the task.
Which set of values describes the specified task?
A) Duration shows 4 days; Work shows 8 hours
B) Duration shows 4 days; Work shows 16 hours
C) Duration shows 2 days; Work shows 0 hours
D) Duration shows 2 days; Work shows 8 hours
E) Duration shows 2 days; Work shows 16 hours
4. Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday. John, a team member, asks to take Thursday off from work. He will work on Saturday to adjust this time. You need to ensure that the change in John's working time is reflected in the project schedule. What should you do?
A) In the Resource Information window for John, select the inactive option for Thursday and cancel the selection of the inactive option for Saturday.
B) Update the resource calendar for John by making Thursday as a non-working day and Saturday as a working day.
C) Update the project calendar for John by making Thursday as a non-working day and Saturday as a working day.
D) In the Resource Information window for John, change John's availability by modifying the Available From and Available To dates for Thursday to 0 percent and for Saturday to 100 percent.
5. Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
A) Assign the resource only to tasks that are scheduled on the working days.
B) Change the working time for the resource.
C) Update the base project calendar.
D) Change the maximum units for the resource.
Solutions:
| Question # 1 Answer: D | Question # 2 Answer: B | Question # 3 Answer: B | Question # 4 Answer: B | Question # 5 Answer: B |
Over 72960+ Satisfied Customers

Eunice
Janet
Lynn
Nicole
Sabrina
Vicky
Easy4Engine is the world's largest certification preparation company with 99.6% Pass Rate History from 72960+ Satisfied Customers in 148 Countries.