NEW QUESTION 30
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing authorizations to release material components
- B. Missing reservations for material components
- C. Missing budget for material components
- D. Missing material availability
Answer: A
NEW QUESTION 31
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question
- A. Resource reports
- B. Hierarchical reports
- C. Cost element reports
- D. Structure information system reports
Answer: A,D
NEW QUESTION 32
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.
- A. Usage of cost elements is mandatory.
- B. Sources can be based on line items.
- C. Sales prices are maintained in the DIP profile.
- D. DIP is used to create a quotation.
- E. Material determination is mandatory.
Answer: B,C,D
NEW QUESTION 33
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.
- A. Automatic activation with assignment to an investment program
- B. Automatic activation with the first actual posting
- C. Automatic activation with budget assignment
- D. Background activation (CJBV - Activate Availability Control)
Answer: C,D
NEW QUESTION 34
The various work packages in the project are described as individual______________. Choose the correct answer.
- A. Tasks
- B. Project definitions
- C. Activities
- D. WBS elements
Answer: D
NEW QUESTION 35
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
- A. Use an offset of two days for milestone date.
- B. Calculate the start date of the activity and set the constraint "Must start on" accordingly.
- C. Use an offset of two days for the requirement date of the material component
- D. Use an offset of two days for the relationship of both activities.
Answer: A,D
NEW QUESTION 36
Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
- A. Activate availability control For projects in the control area. Enter the plan data for each WBS element.
- B. Activate commitment
- C. Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.
- D. management in the project definition. Enter the budget in the master data of the top WBS element.
- E. Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.
Answer: E
NEW QUESTION 37
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Data entry profile
- B. Network type
- C. Project profile
- D. Network profile
Answer: C
NEW QUESTION 38
What is the reason for assigning billing plans in customer projects?
- A. Billing plans are used for revenue planning.
- B. Billing plans are copied automatically to the sales order item.
- C. Billing plans are prerequisites for quotation creation.
- D. Billing plans enable the billing process to be carried out.
Answer: D
NEW QUESTION 39
You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question
- A. Integrated planning for the network is active
- B. The formula for costing in the work center is incorrect
- C. The Determine Costs indicator in the network header rules out planned cost calculation
- D. The duration is missing in the activity
- E. The activity output price for the activity type and cost center assigned to the work center is not maintained.
Answer: B,C,E
NEW QUESTION 40
Resources
You Want assign milestone to WBS element? For what can you use these milestone.
- A. To set an actual finish date for WBS element-
- B. To start workflow task.
- C. For trend analysis.
- D. To create standard network
Answer: C
NEW QUESTION 41
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?
- A. The maintenance orders must be assigned as sub-networks.
- B. The maintenance orders must be assigned to the same plant as the network.
- C. The maintenance order s must be assigned to the same budget profile as the project definition.
- D. The maintenance orders must be assigned to WBS element.
Answer: B
NEW QUESTION 42
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?
- A. Set up the requirement date aligned with the activity start date and an offset of 5 days
- B. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
- D. Set up the requirement date manually as February 5.
Answer: C
NEW QUESTION 43
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Parameters for the network type
- B. Project profile
- C. Network type
- D. Network profile
Answer: C
NEW QUESTION 44
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
- A. Multiple project simulations can be used simultaneously.
- B. Project simulations can create purchase requisitions.
- C. Project simulations can be created without using an operational project as a template.
- D. Project simulations can be used to plan structures and costs.
- E. Project simulations allow posting of actual data.
Answer: A,C,D
NEW QUESTION 45
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.
- A. Operating concern
- B. Controlling area
- C. Company code
- D. Plant
- E. Sales organization
Answer: B,C,D
NEW QUESTION 46
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.
- A. Project versions can be created automatically based on user status.
- B. Project versions can be changed.
- C. Manually created project versions always require a project version profile.
- D. Project versions are mandatory for Milestone Trend Analysis (MTA).
Answer: B,D
NEW QUESTION 47
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.
- A. Allow business processes forbidden by SAP system status
- B. Restrict setting user status for individual users
- C. Utilize priorities for setting the user status
- D. Ensure user status must always be set manually
Answer: B,D
NEW QUESTION 48
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?
- A. Requirements class
- B. Schedule line category
- C. Item category
- D. Requirements type
Answer: C
NEW QUESTION 49
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.
- A. Production version
- B. Material
- C. Location
- D. Resource
Answer: C,D
NEW QUESTION 50
......