The SAP C-TS412-2021 exam is ideal for individuals who have experience in project management and are interested in gaining a deeper understanding of SAP S/4HANA Project Systems. SAP Certified Application Associate - SAP S/4HANA Project Systems certification exam covers a wide range of topics, including project planning, project execution, project monitoring, and project closing. Candidates who take the exam will be tested on their knowledge of the SAP S/4HANA Project Systems module and its integration with other SAP modules. The SAP C_TS412_2021 certification exam is a great way for professionals to showcase their expertise in SAP S/4HANA Project Systems and enhance their career prospects in this field.
SAP C-TS412-2021 exam is designed for individuals who want to become certified SAP Application Associates with a focus on SAP S/4HANA Project Systems. SAP Certified Application Associate - SAP S/4HANA Project Systems certification demonstrates that the candidate has a comprehensive understanding of the SAP S/4HANA Project Systems application, including the ability to configure and implement the application in real-world scenarios. C-TS412-2021 exam covers a range of topics, including project planning, resource management, and cost management, among others.
NEW QUESTION # 11
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question
- A. The factory calendar in the work center used for the internal processing activity
- B. An activated Scheduling indicator in the control key of the internal processing activity
- C. Whether the work for the internal activity is greater than its duration
- D. The relationships between activity elements
- E. The unit (for example, hour, day) of the field Normal Duration field of the activity
Answer: A,B,D
Explanation:
The scheduling of internal processing activities is influenced by several factors, such as the control key, the activity elements, and the factory calendar. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The scheduling indicator in the control key determines whether an activity is included in scheduling or not. The activity elements are subordinate units of an activity that represent partial tasks or work packages. The relationships between activity elements define the logical sequence and dependencies of the partial tasks. The factory calendar is a parameter that defines the working days and holidays for a work center. The factory calendar affects the duration and dates of an activity that uses the work center. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 12
You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain?
- A. Basic dates of the network activity
- B. Forecast dates of the WBS
- C. Basic dates of the WBS
- D. Actual dates of the network activity
Answer: A
Explanation:
To determine the requirement date for a material component assigned to a network activity, you have to maintain the basic dates of the network activity. The basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. The requirement date for a material component is derived from the basic start date of the activity to which it is assigned. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 13
You want to assign milestones to WBS elements. For what can you use these milestones? Note: There are 2 correct Answers to this question.
- A. For trend analysis
- B. To set an actual finish date for WBS elements
- C. To start workflow tasks
- D. To transfer the actual date to the billing plan
Answer: A,D
NEW QUESTION # 14
Cost & Budget.
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Settlement rules
- B. Costing Sheet
- C. Investment profile.
- D. Results analysis key
Answer: A
NEW QUESTION # 15
How can you confirm the working hours of different work centers for a single activity?
- A. Create multiple confirmations for the activity and use the appropriate work center for each confirmation
- B. Enter multiple work centers within a single confirmation
- C. Enter direct activity allocation assigning multiple work centers
- D. Assign multiple work centers to the activity
Answer: A
NEW QUESTION # 16
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.
- A. Plant
- B. Controlling area
- C. Planning department
- D. Company code
Answer: B
Explanation:
"The controlling area that you specify when you create a project definition is unique for the entire project. You specify the controlling area just once when you create the project." Reference: 2
NEW QUESTION # 17
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?
- A. Project profile
- B. Data entry profile
- C. Network profile
- D. Network type
Answer: A
NEW QUESTION # 18
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
- A. You can always maintain the actual start and finish date of a WBS element
- B. You can only maintain the actual start of a WBS element if the finish date is not maintained
- C. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
- D. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
Answer: A,C
Explanation:
If you are using WBS elements and activities are not assigned, you can always maintain the actual start and finish date of a WBS element manually or automatically. However, you can only maintain the actual start if the WBS element has the status "Released" or "Partially released", which means it is ready for processing or partially ready for processing. You can maintain the actual finish regardless of the status of the WBS element. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 19
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.
- A. Released WBS elements, activities, and/or activity elements
- B. A header-account-assigned network that is assigned to a sales order item
- C. A dynamic item processor (DIP) profile with the appropriate settings
- D. An activity-account-assigned network that is assigned to a sales order item
Answer: A,C
NEW QUESTION # 20
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question
- A. Saving a supplier invoice
- B. Saving a goods receipt
- C. Saving a service entry shee
- D. Saving a purchase order
Answer: B,C
NEW QUESTION # 21
Materials
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).
- A. With delivery from projects you can generate purchase requisitions for sub-contractors.
- B. With delivery from projects good receipt are automatically posted while saving.
- C. With the delivery from project you can deliver material component assigned to your network.
- D. With delivery from projects You can generate goods issues for project without creating delivery documents.
Answer: D
NEW QUESTION # 22
Cost and Budget
What function are available for period end-closing in the project System?
- A. Result analysis
- B. Progress analysis
- C. Milestone trend analysis
- D. Settl ement
- E. Confirmation
Answer: A,B,C
NEW QUESTION # 23
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.
- A. The factory calendar in the work center used for the internal processing activity
- B. An activated Scheduling indicator in the control key of the internal processing activity
- C. Whether the work for the internal activity is greater than its duration
- D. The relationships between activity elements
- E. The unit (for example, hour, day) of the field Normal Duration field of the activity
Answer: A,B,D
NEW QUESTION # 24
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
- A. A workflow can be triggered to inform the purchasing group.
- B. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
- C. The purchase order is updated automatically to match the new quantity while saving the project.
- D. The system automatically creates a new purchase requisition with the difference to the original quantity.
Answer: A
NEW QUESTION # 25
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question
- A. Automatically, using the requirement date and the replenishment lead time
- B. When releasing a network or an activity
- C. Using a standard milestone activity
- D. Immediately, by saving the project
Answer: A,B
NEW QUESTION # 26
Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question
- A. Activities with the time constraint "Must start on" always have a negative float time
- B. The maximum size of a free float is as large as the total float of an activity
- C. Float time can be negative
- D. By default, critical activities have a float time, which is less than or equal to zero
- E. The float time of WBS elements is calculated by extrapolation
Answer: A,B,C
NEW QUESTION # 27
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
- A. Milestone
- B. Activity
- C. Activity element
- D. Network header
Answer: B
Explanation:
To maintain constraints for start dates, you can use activities. Activities are structural elements of a network that represent tasks or partial tasks within a project. Constraints are parameters that define fixed dates or time intervals for activities or networks. Constraints can be used to influence the scheduling of project objects and to ensure that certain deadlines are met. You can maintain constraints for start dates or finish dates of activities or networks in the project builder or the project planning board. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 28
Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board.
Note : there are 3 correct answers for this question.
- A. Display of project cost plan.
- B. Display of project -relevant purchase order.
- C. Display of plant maintenance orders for activities.
- D. Display of production orders assigned to WBS element.
- E. Using specific color management for Gantt Chart.
Answer: C,D,E
Explanation:
The Project Planning Board is a tool that allows you to create and update Gantt charts for your projects. Some of the characteristics of the Project Planning Board are:
Display of production orders assigned to WBS elements: You can use the Project Planning Board to display production orders that are related to WBS elements in your project. You can also create, change, or confirm production orders from the Project Planning Board.
Display of plant maintenance orders for activities: You can use the Project Planning Board to display plant maintenance orders that are related to activities in your project. You can also create, change, or confirm plant maintenance orders from the Project Planning Board.
Using specific color management for Gantt Chart: You can use the Project Planning Board to customize the colors and shapes of the bars and symbols in the Gantt chart according to various criteria, such as status, priority, or person responsible. You can also define your own color schemes and save them as variants. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002
NEW QUESTION # 29
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Line item report for budgets
- B. Structure overview for budgets
- C. Cost element report on budget updates
- D. Hierarchical report on budget updates
Answer: D
Explanation:
A hierarchical report on budget updates is a standard report type that provides an overview of adjustments on the budget for WBS elements within your project. A hierarchical report on budget updates displays the budget values and changes for each WBS element in a hierarchical structure. You can use various selection criteria and display options to customize the report according to your needs. You can also access detailed information on individual budget values or changes by choosing drilldown functions. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 30
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use ?
- A. Bottom-up
- B. Strict bottom-up
- C. Free planning
- D. Top-down
Answer: C
Explanation:
To extrapolate the basic dates of subordinate WBS elements without taking into account the basic dates of higher-level WBS elements, you can use free planning as the planning method for basic dates. Free planning is a type of planning method for basic dates that allows you to plan dates for WBS elements without any restrictions or dependencies on other WBS elements. Free planning does not consider any hierarchical relationships between WBS elements when calculating their dates. Free planning gives you maximum flexibility and control over your date planning for WBS elements. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 31
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question
- A. Generate purchase requisition
- B. Generate delivery
- C. Stock transfer posting
- D. Confirm production order
- E. Cancel goods issue
Answer: A,C,E
Explanation:
Project-Oriented Procurement (ProMan) supports various business transactions that are related to project procurement. Some of these transactions are:
Stock transfer posting: You can use this transaction to transfer project stock from one storage location to another within the same plant or between different plants.
Generate purchase requisition: You can use this transaction to create a purchase requisition for a material or service that is required for a project.
Cancel goods issue: You can use this transaction to reverse a goods issue posting for a material that was issued from project stock. Reference: https://help.sap.com/saphelp_erp60_sp/helpdata/EN/8e/8bc95360267214e10000000a174cb4/frameset.htm
NEW QUESTION # 32
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question
- A. If the reduction strategy is set in each activity
- B. If the maximum reduction level is less than 100
- C. If the appropriate reduction type is set in the parameters for network scheduling
- D. If the reduction strategy is set in the network header
Answer: B,C
Explanation:
The possible reasons to check if reductions did not reduce the scheduled duration of all internally-processed activities in your project after overall network scheduling are if the maximum reduction level is less than 100 or if the appropriate reduction type is set in the parameters for network scheduling. Reductions are functions that allow you to reduce the scheduled duration of activities and networks by changing their work or capacity requirements based on various strategies and criteria. Reductions can help you optimize your project schedule and meet deadlines or milestones. The possible reasons to check if reductions did not reduce the scheduled duration of all internally-processed activities in your project after overall network scheduling are:
If the maximum reduction level is less than 100: The maximum reduction level is a parameter that defines how much an activity or a network can be reduced as a percentage of its original duration. The maximum reduction level can be specified in Customizing for Project System under Structures Operative Structures Networks Define Reduction Strategies
NEW QUESTION # 33
The various work packages in the project are described as individual______________. Choose the correct answer.
- A. Tasks
- B. Activities
- C. WBS elements
- D. Project definitions
Answer: C
NEW QUESTION # 34
......
SAP C-TS412-2021 certification exam is a valuable credential for individuals interested in demonstrating their expertise in project management using SAP S/4HANA. With the right preparation and study materials, candidates can successfully pass C-TS412-2021 exam and earn this highly respected certification.
C-TS412-2021 Dumps for SAP Certified Application Associate Certified Exam Questions and Answer: https://www.easy4engine.com/C-TS412-2021-test-engine.html
C-TS412-2021 Free Exam Study Guide! (Updated 112 Questions): https://drive.google.com/open?id=1MSKL8piUtcTHNNnvx6H1r95VH_laf8OC