AACE International is a non-profit professional association that provides education and certification to professionals in the project management and cost engineering fields. One of the certifications offered by AACE International is the Planning & Scheduling Professional (PSP) certification. The PSP certification is designed for professionals who specialize in planning and scheduling in the construction, engineering, and project management industries.


AACE International AACE-PSP Certification Exam is an excellent way for professionals to demonstrate their expertise in project planning and scheduling. Planning & Scheduling Professional (PSP) Exam certification is recognized worldwide and is often required for project management roles in many organizations. It is a challenging exam that requires candidates to have a solid understanding of project planning and scheduling concepts. However, with the right preparation and experience, passing the exam can be a significant achievement for any project management professional.


Preparing for the AACE-PSP certification exam requires a significant commitment of time and effort. Candidates must have a thorough understanding of project management principles, tools, and techniques, and must be able to apply this knowledge to solve real-world problems. There are many study resources available, including textbooks, online courses, and practice exams, to help candidates prepare for the exam.

 

NEW QUESTION # 33
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  • A. Has yet to be completed.
  • B. Is a milestone.
  • C. Was completed in the past.
  • D. It is on the critical path.

Answer: A


NEW QUESTION # 34
What is the workweek period for this project?

  • A. Monday through Friday
  • B. Monday through Saturday
  • C. Sunday through Friday
  • D. Sunday through Saturday

Answer: D


NEW QUESTION # 35
The linear scheduling velocity diagram has the following two-axis:

  • A. Time and location
  • B. Location and crew size
  • C. Time and rate of progress
  • D. Time and crew size

Answer: C


NEW QUESTION # 36
Why does activity 11001 not show successor activities?

  • A. The scheduler forgot to add the successor activities
  • B. It is the final activity for the required work for the project
  • C. It is the penultimate work required for the project
  • D. The early finish and late finish are circular

Answer: B


NEW QUESTION # 37
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?

  • A. 4 days
  • B. 5 days
  • C. 6 days
  • D. 8 days

Answer: C


NEW QUESTION # 38
Determine the correct formula and date for the late finish for Activity 2001.

  • A. LS.2002- 1 day-> 08-29-01.
  • B. LF.2001 - 1 day -> 08-28-01.
  • C. LS.2002 + 1 day -> 08-30-01.
  • D. LS.2002 - 1 day -> 08-28-01.

Answer: D


NEW QUESTION # 39
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

  • A. 06-11-02.
  • B. 06-18-02.
  • C. 06-05-02.
  • D. 06-04-02.

Answer: C


NEW QUESTION # 40
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. The schedule is projecting an "early completion".
  • B. Certain activities in the critical path have no successors.
  • C. Different calendars are assigned to certain activities in the logical chain.
  • D. The schedule has too much detail to reflect an accurate critical path.

Answer: B


NEW QUESTION # 41
Determine the correct formula and date for the late finish for Activity 2002.

  • A. LS.2003 - 1 day -> 10-06-01.
  • B. LS.2003 + 1 day -> 10-07-01.
  • C. LS.2003 - 1 day -> 11.06.01.
  • D. LS.2003 - 1 day -> 10-05-01.

Answer: D


NEW QUESTION # 42
What method offers the best chance of the schedule being used effectively to implement the project in the field?

  • A. Obtain consent and agreement to the schedule from the key project personnel.
  • B. Issue detailed schedule updates as frequently as possible.
  • C. Include detailed and stringent set of scheduling specifications in the contract.
  • D. Allow large time contingencies on milestones and completion deadlines.

Answer: A


NEW QUESTION # 43
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.

  • A. Budgeted cost of work performed (BCWP)
  • B. Budget at completion (BAC)
  • C. Budgeted cost of work scheduled (BCWS)
  • D. Estimate at completion (EAC)

Answer: B


NEW QUESTION # 44
Determine the correct formula and date for the late start for Activity 9001.

  • A. LS.6001 Dur.6001 -> 11-20-02.
  • B. LF.9001 Dur.9001 -> 11-20-02.
  • C. There is insufficient data provided to calculate the answer.
  • D. The early finish is required in order to determine the answer.

Answer: B


NEW QUESTION # 45
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

  • A. Tabular listing of activities showing duration, calendar ID, early and late dates
  • B. Detailed listing of working days for each calendar used
  • C. Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID
  • D. Assigned party responsibility for each work task

Answer: D


NEW QUESTION # 46
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  • A. Front end loading.
  • B. Preferential logic.
  • C. Start and finish constraints.
  • D. Multiple calendars.

Answer: A


NEW QUESTION # 47
All the following describe the critical path of a schedule EXCEPT:

  • A. The series of activities having the least amount of total float.
  • B. Frequently defined as the shortest path through the schedule.
  • C. Determined by network logic and is the chain of activities that controls the overall project completion time.
  • D. Changed by redefining the network logic or changing activity durations or both.

Answer: B


NEW QUESTION # 48
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. The activities occur in series with a 15-day lag.
  • B. The activities run concurrently.
  • C. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
  • D. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.

Answer: A


NEW QUESTION # 49
What owner action could have mitigated the late completion of the project?

  • A. Self-perform more of the work.
  • B. Use a procurement agent to monitor and expedite equipment deliveries.
  • C. Hire a more senior project manager.
  • D. Prepare better structural steel drawings.

Answer: B


NEW QUESTION # 50
Project schedules help control all of the following EXCEPT for_____________________.

  • A. Cost
  • B. Time
  • C. Quality
  • D. Resources

Answer: C


NEW QUESTION # 51
Determine the correct formula and date for the late finish for Activity 9004.

  • A. LS.10002 + 1 day -> 11-29-03.
  • B. LS.10002 - Lag.7 - l day -> 11-20-03.
  • C. LS.10002 - 1 day -> 11-27-03.
  • D. LS.10002^ Lag.7 + i day -> 11-20-03.

Answer: D


NEW QUESTION # 52
At a minimum, periodic reporting must be done at what interval?

  • A. As requested by the owner.
  • B. As specified in the contract documents.
  • C. Monthly.
  • D. As requested by the project manager.

Answer: B


NEW QUESTION # 53
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?

  • A. 3 cranes
  • B. 4 cranes
  • C. 2 cranes
  • D. 1 crane

Answer: C


NEW QUESTION # 54
Free float is the

  • A. Difference between the early dates and late dates of an activity.
  • B. Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.
  • C. Difference between the early finish dates and late finish dates of an activity.
  • D. Difference In float value of the critical path activities and the float value of the specific activity being analyzed.

Answer: B


NEW QUESTION # 55
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

  • A. 8 work days
  • B. 15 workdays
  • C. 18 work days
  • D. 7 work days

Answer: A


NEW QUESTION # 56
......