Quality C-ACTIVATE13 PDF Dumps - C-ACTIVATE13 Exam Questions
Most UptoDate SAP C-ACTIVATE13 Exam Dumps PDF 2022
C-ACTIVATE13 Exam Certification Details:
| Duration: | 180 mins |
| Level: | Associate |
| Exam: | 80 questions |
| Languages: | English, Japanese, Russian |
| Cut Score: | 65% |
| Sample Questions: | SAP C-ACTIVATE13 Exam Sample Question |
NEW QUESTION 69
Which of the following are not phases of the SAP Activate methodology?
There are 2 correct answers to this question.
Response:
- A. Preparation
- B. Prepare
- C. Go-Live & Support
- D. Realize
Answer: A,C
NEW QUESTION 70
Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud' transition path?
Please choose the correct answer.
Response:
- A. Solution Validation and Delta Design
- B. Simplification and Custom Code Impact Analysis
- C. Fit-to-standard
- D. Setup and Enablement
Answer: C
NEW QUESTION 71
How often will an upgrade be performed on an SAP S/4HANA Cloud, Single Tenant Edition environment?
Please choose the correct answer.
Response:
- A. Every year
- B. Schedule is defined by Service Level Agreement for SAP HANA Enterprise Cloud and SAP S/4HA NA Cloud, Single Tenant Edition Services
- C. Every quarter
- D. One upgrade and two feature packs per year
Answer: B
NEW QUESTION 72
What is SAP Activate?
Please choose the correct answer.
Response:
- A. A methodology for each of the deployment modes (cloud , on-premise, hybrid)
- B. A bundle of ASAP , SAP Launch , and Rapid Deployment Solutions
- C. A step-by-step instruction on how to remove from SAP best practices to your custom solution
- D. A combination of SAP best practices , methodology, and guided configuration
Answer: D
NEW QUESTION 73
How would you describe the Explore phase in the "New Implementation of SAP S/4HANA Cloud" transition path?
Please choose the correct answer.
Response:
- A. Solution Validation and Delta Design
- B. Simplification and Custom Code Impact Analysis
- C. Fit-to-standard
- D. Setup and Enablement
Answer: C
NEW QUESTION 74
Which of the following tools are used for rapid database migration?
There are 2 correct answers to this question.
Response:
- A. SWPM (software provisioning manager)
- B. Software Update Manager (SUM)
- C. SAP Solution Manager
- D. Database Migration Option (DMO)
Answer: B,D
NEW QUESTION 75
Which tool can you use to collaborate with other SAP Activate methodology practitioners?
Please choose the correct answer.
Response:
- A. SAP Implementation Assistant
- B. SAP Solution Manager
- C. Roadmap Viewer
- D. SAP Jam
Answer: D
NEW QUESTION 76
What is the primary purpose of the SAP Activate Methodology?
Please choose the correct answer.
Response:
- A. To enable access to the SAP ecosystem
- B. To provide end-to-end Application Lifecycle Management
- C. To manage solution documentation
- D. To provide the sequence of actions in the project
Answer: D
NEW QUESTION 77
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?
There are 3 correct answers to this question.
Response:
- A. Validation Workshops
- B. Solution Scope and Value Determination
- C. Baseline Build
- D. Design for the Gaps and Deltas
- E. Data Migration Approach
Answer: A,D,E
NEW QUESTION 78
Which of the following can be used to navigate through the roadmap?
There are 2 correct answers to this question.
Response:
- A. Workstreams
- B. Phases
- C. Deliverables
- D. Tasks
Answer: A,D
NEW QUESTION 79
Which artifacts are part of the Solution Adoption work stream?
There are 3 correct answers to this question.
Response:
- A. System Go live Announcement (order)
- B. Project Business Case
- C. Detailed Design - Business Process
- D. Business Transformation Review (Point of View)
- E. Project Plan
Answer: A,B,D
NEW QUESTION 80
What is the purpose of a firm-up sprint?
Please choose the correct answer.
Response:
- A. To perform String test
- B. To run end-to-end integration test
- C. To demonstrate functionality from previous sprint
- D. To revise a release plan and sprint plan
Answer: A
NEW QUESTION 81
Which of the following scenarios are enabled for the "Selective Data Transition" transition path with the SAP Landscape Transformation tool?
There are 3 correct answers to this question.
Response:
- A. System Consolidation
- B. System Upgrade
- C. Security Migration
- D. Extraction of Business Units
- E. Consolidation through online data replication
Answer: A,D,E
NEW QUESTION 82
Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what sequence of activities do you perform in the Explore Phase?
Please choose the correct answer.
Response:
- A. a. Set reference value
b. Prioritize initial backlog
c. Conduct Delta Design workshops
d. Conduct Solution Validation workshops - B. a. Conduct Solution Validation workshops
b. Conduct Delta Design workshops
c. Set reference value
d. Prioritize initial backlog - C. a. Conduct Solution Validation workshops
b. Set reference value
c. Prioritize initial backlog
d. Conduct Delta Design workshops - D. a. Set reference value
b. Conduct Solution Validation workshops
c. Prioritize initial backlog
d. Conduct Delta Design workshops
Answer: D
NEW QUESTION 83
What is the minimum number of quality gates mandated by the SAP Activate methodology?
Please choose the correct answer.
Response:
- A. 0
- B. 1
- C. 2
- D. 3
Answer: D
NEW QUESTION 84
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
Response:
- A. Deploy
- B. Explore
- C. Prepare
- D. Realize
Answer: A
NEW QUESTION 85
What does SAP Activate recommend to keep team members informed and aligned?
Please choose the correct answer.
Response:
- A. Daily e-mail status updates to project manager
- B. Daily status meeting with project manager
- C. Daily team stand-up meeting
- D. Daily progress review meeting with sponsor
Answer: C
NEW QUESTION 86
Which collaboration features can SAP Activate Jam users access?
There are 2 correct answers to this question.
Response:
- A. Ask questions
- B. Tweet questions
- C. Comment on documents
- D. Update Key Deliverable wikis
Answer: A,C
NEW QUESTION 87
Which activity helps the Project Team add User Stories to the Product Backlog?
Please choose the correct answer.
Response:
- A. Conducting the Solution Validation workshop
- B. Assessing Project Risks
- C. Preparing a Project Schedule
- D. Planning the User Acceptance Test
Answer: A
NEW QUESTION 88
What is SCRUM of SCRUMS?
Please choose the correct answer.
Response:
- A. Frequent inspection of code and configuration prior to quality gates
- B. Alternative to regular SCRUM process for smaller teams
- C. Integration meeting between the various project teams
- D. Mechanism for gathering and validating requirements
Answer: C
NEW QUESTION 89
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition. What is the correct sequence of selected key deliverables across the project phases?
Please choose the correct answer.
Response:
- A. a. Detailed system Assessment
b. Production Readiness Check
c. Code Adjustment
d. Validation of Migration - B. a. Code adjustment
b. Detailed System Assessment
c. Production Readiness Check
d. Validation of Migration - C. a. Detailed system Assessment
b. Code Adjustment
c. Validation of Migration
d. Production Readiness Check - D. a. Production Readiness Check
b. Detailed system Assessment
c. Code Adjustment
d. Validation of Migration
Answer: C
NEW QUESTION 90
......
100% Free SAP Certified Associate C-ACTIVATE13 Dumps PDF Demo Cert Guide Cover: https://www.easy4engine.com/C-ACTIVATE13-test-engine.html
PDF Exam Material 2022 Realistic C-ACTIVATE13 Dumps Questions: https://drive.google.com/open?id=1EG9F0tL2FZYmiE8s0H4ha--Z_l7VSi2H